What do you understand by the term technical analysis? How is it done?
What do you understand by the term technical analysis?
How is it done?
Ans. The success of an enterprise depends upon the
entrepreneur doing the right thing at the right time. Starting a new venture is
a very challenging and rewarding task. A businessman has to take numerous
decisions, right from the conception of a business idea, upon the start of
production. Hence, the identification of the project to be undertaken, requires
an analysis of the project in depth. Therefore, a technical and financial
analysis of the project has to be undertaken.
TECHNICAL ANALYSIS
Analysis of technical and engineering aspects is done
continually when a project is being examined and formulated. Other types of
analyses are dependent and closely intertwined with technical analysis.
Technical analysis is concerned primarily with:
Materials and inputs
An important aspect of technical appraisal is concerned
with defining the materials and inputs required, specifying their properties in
some detail, and setting up their supply programme. There is an intimate
relationship between the study of materials and inputs and other aspects of
project formulation, particularly those concerned with location, technology,
and equipment.
Materials and inputs may be classified into four broad
categories:
(i) raw materials,
(ii) processed industrial materials and components,
(iii) auxiliary materials and factory supplies, and
(iv) utilities.
(i) Raw materials— Raw
materials (processed and /or semi processed)may be classified into four types:
(i) agricultural products, (ii) mineral products, (iii) livestock and forest
products,
and (iv) marine products.
(ii) Processed industrial materials and components— Processed industrial materials and components (base metals,
semi-processed materials, manufactured parts, components, and sub-assembly
represent an important input for a number of industries. In studying them the
following questions need to be answered: In the case of industrial materials,
what are their properties?
What is the total requirement of the project?
What quantity would be available from domestic
source?
What quantity would be available from foreign sources?
How dependable are the supplies?
What has been the past trend in prices?
What is the likely future behaviour of prices?
(iii) Auxiliary materials and factory supplies— In addition to the basic raw materials and processed
industrial materials and components, a manufacturing project requires various
auxiliary materials and factory supplies, like chemicals, additives, packaging
materials, paints, varnishes, oils, grease, cleaning materials, etc.The
requirements of such auxiliary materials and supplies should be taken into
account in the feasibility study.
(iii) Utilities— A
broad assessment of utilizes (power, water, steam, fuel, etc.) may be made at
the time of input study though a detailed assessment can be made only after
formulating the project with respect to location, technology, and plant
selection. Since the successful operation of a project critically depends on
adequate availability of utilities the following points should be raised whiled
conducting the input study:
What quantities are required?
What are the sources of supply?
What would be the potential availability?
What are the likely shortages/bottlenecks?
What measures may be taken to augment supplies.
Production technology
For manufacturing a product/service often two or more
alternative technologies are available. For example:
Steel can be made either by the Bessemer
process or the open hearth process.
Cement can be made either by the dry
process or the wet process.
Soda can be made by the electrolysis method
or the chemical method.
Paper, using bagasse as the raw material,
can be manufactured by the kraft process or the soda process or the simon cusi
process.
Vinyl chloride can be manufactured by using
one of the following reactions: acetylene on hydrochloric acid or ethylene or
chlorine.
Choice of technology
The choice of technology is influenced by a variety of
considerations:
(i) Principal inputs— The choice of technology depends on the principal inputs
available for the project. In some cases, the raw materials available
influences the technology chosen. For example,the quality of limestones
determines whether the wet or dry process should be used for a cement plant. It
may be emphasized that a technology based on indigenous inputs may be
preferable to one based on imported inputs because of uncertainties characterizing
imports, particularly in a country like India.
(ii) Investment outlay and production cost— The effect of alternative technologies of investment outlay
and production cost over a period of time should be carefully assessed.
(iii) Use by other units— The technology adopted must be proven by successful use by
other units, preferably in India.
(iv) Product mix— The technology chosen must be judged in terms of the total
product-mix generated by it, including saleable byproducts.
(v) Latest developments— The technology adopted must be based on latest development
in order to ensure that the likelihood of technological obsolescence in the
near future, at least, is
minimized.
(vi) Ease of absorption— The ease with which a particular technology can be absorbed
can influence the choice of technology. Sometimes a high-level technology may
be beyond the absorptive capacity of a developing country which may lack
trained personnel to handle that technology.
Product Mix
The choice of product mix is guided primarily by market
requirements. In the production of most of the items variations in size and
quality are aimed the production of most of the items, variations in size and
quality are aimed at satisfying a broad range of customers. For
example,production of shoes to different customers. It may be noted that
sometimes slight variations in quality can enable a company to expand its
market and enjoy higher profitability. For example, a toilet soap manufacturing
unit may by minor variation in raw material, packaging, and sales promotion
offer a high profit margin soap to consumers in upper-income brackets. While
planning the production facilities of the firm, some flexibility with respect
to the product mix must be sought. Such flexibility enables the firm to alter its
product mix in response to changing market conditions and enhances the power of
the firm to survive and grow under differentsituations. The degree of
flexibility chosen may be based on a careful analysis of the additional
investment requirements for different degrees of flexibility.
Plant capacity
Plant capacity (also referred to as production as capacity)
refers to the volume or number of units that can be manufactured during a given
period. Several factors have a bearing on the capacity decision.
(i) Technological requirement— For many industrial projects,particularly in process type
industries, there is a certain minimum economic size determined by the
technological factor. For example, a cement plant should have a capacity of at
least 300 tonnes per day in order to use the rotary kiln method; otherwise, it
has to employ the vertical shaft method which is suitable for lower capacity.
(ii) Input constraints— In a developing country like India, there may be
constraints on the availability of certain inputs. Power supply may be limited;
basic raw materials may be scarce; foreign exchange available for imports may
be inadequate. Constraints of these kinds should be borne in mind while
choosing the plant capacity.
(iii) Investment cost— When serious input constraints do not obtain, the
relationship between capacity and investment cost is an important
consideration. Typically, the investment cost per unit of capacity decreases as
the plant capacity increases.
(iv) Market conditions— The anticipated market for the product/service has an
important bearing on plant capacity. If the market for the product is likely to
be very strong, a plant of higher capacity is preferable. If the market is
likely to be uncertain, it might be advantageous to start with a smaller capacity.
If the market, starting from a small base, is expected to grow rapidly, the
initial capacity may be higher than the initial level of demand further
additions to capacity may be affected with the growth of market.
(v) Resources of the firm— The resources, both managerial and financial, available to
a firm define a limit on its capacity decision. Obviously, a firm cannot choose
a scale of operations beyond its financial resources and managerial capability.
(vi) Governmental policy— The capacity level may be constrained by governmental
policy. Given the level of additional capacity to be created in an industry,
within the licensing framework of the government the government may decide to
distribute the additional capacity among several firms.
Location and site
The choice of location and site follows an assessment of
demand, size, and input requirement. Though often used synonymously, the terms
'location' and 'site' should be distinguished. Location refers to a fairly
broad area like a city, an industrial zone, or a coastal area; site refers to a
specific piece of land where the project would be set up. The choice of
location is influenced by a variety of considerations: proximity to raw
materials and markets, availability of infrastructure, governmental policies,
and other factors.
(i) Proximity to raw materials and markets— An important consideration for location is the proximity to
sources of raw materials and nearness to the market for final products. In
terms of a basic locational model, the optimal location is one where the total
cost (raw material transportation cost plus production cost plus distribution
cost for final product) is minimized. This generally implies that:
(i) a resource-based project like a cement plant or a steel
mill should be located close the source of basic material (for example,
limestone in the case of a cement plant and iron-ore in
the case of a steel plant);
(ii) a project based on imported material may be located
near a port; and
(iii) a project manufacturing a perishable product should
be close to the center of consumption.
However, for many industrial products proximity to the
source of raw material or the center of consumption may not be very important.
Petro-chemical units or refineries, for example, may be located close to the
source of raw material, or close to the center of consumption, or at some
intermediate point.
(ii) Availability of infrastructure— Availability of power,transportation, water, and
communications should be carefully assessed before a location decision is
made.Adequate supply of power is a very important condition for location—
insufficient power can be a major constraint, particularly in the case of an
electricity-intensive project like an aluminium plant. In evaluating power
supply the following should be looked into: the quantum of power available, the
stability of power supply, the structure of power tariff, and the investment
required by the
project for a tie-up in the network of the power supplying
agency. For transporting the inputs of the project and distributing the outputs
of the project, adequate transport connections—whether by rail, road, sea,
inland water, or air— are reqired. The availability, reliability and cost of
transportation for various alternative locations should be assessed.Given the
plant capacity and the type of technology, the water requirement for the
project can be assessed. Once the required quantity is estimated, the amount to
be drawn from the public utility system and the amount to be provided by the
project from surface or sub-surface sources may be determined. For doing this
the following factors may be examined: relative costs, relative
dependabilities, and relative qualities. In addition to power, transport, and
water, the project should have adequate communication facilities like telephone
and fax etc.
(iii) Governmental policies— Governmental policies have a bearing on location. In the
case of public sector projects, location is directly decided by the government.
It may be based on a wider policy for regional dispersion of industries. In the
case of private sector projects, location is influenced by certain governmental
restrictions and inducements. The government may prohibit the setting up of
industrial projects in certain areas which suffer from urban congestion. More
positively, the government offers inducements for establishing industries in
backward areas. These inducements consist of outright
subsidies, concessional finance, tax relief, and other benefits.
(iv) Other factors— Several other factors have to be assessed before reaching a location
decision: ease in coping with environmental pollution, labour situation,
climatic conditions, and general living conditions. A project may cause
environmental pollution in various ways:
it may throw gaseous emission; it may produce liquid and
solid discharges; it may cause noise, heat, and vibrations. The location study
should analyse the costs of mitigating environmental pollution to tolerable
levels at alternative locations.The labour situation at alternative locations
may be assessed in terms of:
(i) the availability of labour, skilled, semi-skilled, and
unskilled;
(ii) the past trends in labour rates, the prevailing labour
rates, and the projected labour rates; and
(iii) the state of industrial relations judged in terms of the
frequency and severity of strikes
and lockouts and the attitudes of labour and management.
The climatic conditions (like temperature, humidity, wind,
sunshine, rainfall, snowfall, dust and fumes, flooding, and earthquakes) have
an important influence on location. They have a bearing on cost as they
determine the extent of air-conditioning, de-humidification, refrigeration,
special drainage, etc., required for the project. General living conditions,
judged in terms of cost of living, housing situation, and facilities for
education, recreation, transport, and
medical care, need to be assessed at alternative locations.
Machinery and equipment
The requirement of machinery and equipment is dependent on
production technology and plant capacity. It is also influenced by the type of
project. For a process-oriented industry, like a petrochemical unit,machinery
and equipment required should be such that the various stages have to be
matched well. The choice of machinery and equipment for a manufacturing
industry is somewhat wider as various machines can perform the same function
with varying degrees of accuracy. For example, the configuration of machines
required for the manufacture of refrigerators could take various forms. To
determine the kinds of machinery and equipment requirement for a manufacturing
industry, the following procedure may be followed:
(i) Estimate the likely levels of production over time.
(ii) Define the various machining and other
operations. (iii) Calculate the machine hours required for
each type of operation. (iv) Select machinery and equipment required for each
function. The equipment required for the project may be classified into the
following types: (i) plant (process) equipment, (ii) mechanical equipment,
(iii) electrical equipment, (iv) instruments, (v) controls, (vi) internal
transportation system, and (vii) other machinery and equipment.
In addition to the machinery and equipment, a list should
be prepared of spare parts and tools required. This may be divided into: (i)
spare parts and tools to be purchased with original equipment, and (ii) spare
parts and tools required for operational wear and tear.
Constraints in selecting machinery and equipment— In selecting the machinery and equipment, certain
constraints should be borne in mind:
(i) there may be a limited availability of power to set up an
electricity intensive plant like, for example, a large electric furnace;
(ii) there may be difficulty in transporting a heavy
equipment to a remote location;
(iii) workers may not be able to operate, at least in the initial
periods, certain sophisticated equipment such as numerically controlled
machines;
(iv) the import policy of the government may preclude the
import of certain types of machinery and equipment.
Structures and civil works
Structures and civil works may be divided into three
categories: (i) site preparation and development, (ii) buildings and
structures, and (iii) outdoor works.
(i) Site preparation and development— This covers the following:
(i) grading and leveling of the site, (ii) demolition and
removal of existing structures, (iii) relocation of existing pipelines
cables,roads, powerlines, etc., (iv) reclamation of swamps, draining and
removal of standing water, (v) connections for the following utilities from the
site to the public network: electric power (high tension and low tension),
water (use water and drinking water), communications (telephone, fax, etc.),
roads, railway sidings, and
(vi) other site preparation and developmental work.
(ii) Buildings— Buildings
and structures may be divided into: (i)factory or process buildings; (ii)
ancillary buildings required for stores, warehouses, laboratories, utility
supply centers, maintenance services, and others; (iii) administrative
buildings; (iv) staff welfare buildings, cafetaria, and medical service
buildings; and (v) residential buildings.
(iii) Outdoor works— Outdoor works cover (i) supply and distribution of
utilities (water, electric power, communication, steam and gas); (ii) handling
and treatment of emissions, wastages, and effluents; (iii) transportation and
traffic arrangements (roads, railway tracks, paths, parking areas, sheds,
garages, traffic signals, etc.): (iv) outdoor lighting; (v) landscaping; and
(vi) enclosure and supervision (boundary wall, fencing, barriers, gates, doors,
security posts, etc.).
Project charts and layouts
Once data is available on the principal dimension of the
project— market size, plant capacity, required technology, equipment and civil
works,conditions obtaining at plant site, and supply of inputs to the project—
project charts and layouts may be prepared. These define the scope of the
project and provide the basis for detailed project engineering and estimation
of investment and production costs.
Work Schedule
The work schedule, as its name suggests, reflects the plan
of work concerning installation as well as initial operation. The purpose of
the work schedule is:
To anticipate problems likely to arise
during the installation phase and suggest possible means for coping with them.
To establish the phasing of investments
taking into account availability of finances.
To develop a plant of operations covering
the initial period (the running in period).
Often, it is found that the required inputs like raw
material and power are not available in adequate quantity when the plant is
ready for commissioning, or the plant is not ready when the raw material
arrives.